DAM REMOVAL TIMELINE
![]() |
| Sodom Ditch Project: Completed -Click photo to view album- |
November 7: Construction at the former dam sites is now complete. The bifurcation of Sodom Ditch and the Calapooia River has been reinforced with a large engineered log jam to purposefully deflect flow away from the bank and prevent erosion. Over 1500 feet of riverbed has been carefully constructed to seamlessly connect the bifurcation to the former site of Sodom Dam, which will allow for a properly functioning river conducive to fish habitat and bank stability. Some planting has occurred, with more scheduled for winter to re-vegetate the riverbanks.
![]() |
| Shearer Project: Completed -Click photo to view album- |
![]() |
| Sodom Ditch Re-vegetation November 1, 2011 -Click photo to view album- |
November 1: Willow were planted on a large engineered log jam at the bifurcation of the Calapooia River and Sodom Ditch. The log jam will properly deflect flow and prevent erosion, and the willow will help to stabilize this structure as well as provide crucial riparian habitat.
![]() |
| Sodom Riffle Construction October 26, 2011 -Click photo to view album- |
October 26: With the riffles completed, the coffer dam has been breached and the river is once again free to flow down Sodom Ditch. Construction is now focused on creating vegetated soil lifts along the stream bank, as well as strategically placing engineered log jams and woody debris where appropriate. Vegetation is also being planted along the river bank to create a riparian buffer.
![]() |
| Sodom Riffle Construction Week of 10/24 -Click photo to view album- |
October 24: Work continues to finish the bottom of the channel. The contractor is using fines (sand, clay, small gravels) from stockpiles on-site to seal the riffles. The fine materials are spread over the imported rock surfaces and tracked in. Then, the bucket of the trackhoe is used to drop water over the fine materials. The water transports the sand and clay particles and fills all the small spaces between the larger rock that comprise the riffle.
Margin treatment work will continue along the Sodom, but the bottom of the channel is now sealed. Margin treatment includes installation of vegetated soil lifts, bank shaping, and placement of rock.
![]() |
| Castleberg Backwater Habitat Restoration -Click photo to view album- |
October 6 – BONUS footage: Besides dam removal, the Council has been implementing a variety of other river restoration projects throughout the watershed. An example of this is the construction of several engineered log jams (ELJs) on the Castleberg property near Brownsville. Log jams strategically placed into an area of backflow off of the Calapooia River provide important habitat for endangered salmon species. View the photo album to learn more about the construction of these log jams and the importance of backwater habitat for river ecosystems.
![]() |
| Sodom Riffle Construction Week of 10/5 -Click photo to view album- |
Vegetated soil lifts are what they sound like – soil wrapped with jute fabric with willow cuttings placed on top. Each successive layer steps a foot and half closer to the bank and from the side view, resembles a staircase. Coir logs (made of coconut fibers) are installed in the toe of each layer to provide structure and stability to the lift. This bio-engineering technique provides bank stability by gently shaping the slope and installing a living bank protection (willow). The willow
will slow down the river’s energy, trap sediment, and become deeply rooted, thereby protecting the bank from the river’s erosive forces. The VSLs are being installed with willow cuttings from the project vicinity. This vegetation will root in the coming spring and provide stability at the toe of the bank in areas where bare soil was exposed from project implementation. The coir logs and fabric wraps will provide short-term (3-5 years) stability until the willow become mature.
Large wood jams are being installed on the margins of each riffle. These structures provide bank stability, cover for fish, habitat for insects, and slow water down because of their complex shape and structure, breaking up the River’s velocity.
![]() |
| Sodom Riffle Construction Week of 9/28 -Click photo to view album- |
September 28: Progress continues on construction of the riffles for the Sodom Channel Restoration Project. For the week of September 26th, work has begun on the margin treatments. This involves installation of
wood material into the bench along the channel margin, along with willow clumps harvested from on-site. The final steps include placement of rounded rock which will be washed in with sands and fines. This restoration treatment is being implemented in the Sodom Channel just downstream of the bifurcation.
![]() |
| Sodom Riffle Construction Week of 9/20 -Click photo to view album- |
September 20: Construction continues at the former site of Sodom Dam. Three riffles, designed by River Design Group and constructed by BCI Contracting Inc., will connect the bifurcation (where Sodom Ditch branches out from the Calapooia) to the dam removal site, resulting in a smooth gradient between the regions. Downcutting would occur if the riffles were not installed, which would result in increased water velocity, erosion, and poor habitat for fish and other wildlife.
![]() |
| Shearer Dam Deconstruction -Click photo to view album- |
![]() |
| Shearer Fish Salvage -Click photo to view album- |
![]() |
| Turtle Relocation -Click photo to view album- |
August 11: Three turtles were captured in the riprap downstream of the coffer dam. Since they were in danger of being smooshed by the excavator as work progressed on the site, they were re-located out of harm’s way at the bifurcation.
![]() |
| Fish Passage Celebration -Click photo to view album- |
July 29th: Our Fish Passage Celebration was a great success! We’d like to mention a special thanks to the following people:
Program Sponsors: Oregon Watershed Enhancement Board, Oregon State Parks, American Rivers, and National Oceanic and Atmospheric Administration.
Contractors: River Design Group, BCI Contracting Inc., and Staton Companies.
Event Sponsors: US Forest Service, Calapooia Brewing Company, and Wild Hog in the Woods.
Event Coordinator and Volunteers: Whitney Smith, Kent Davis, Bud & Barbara Baumgartner, Eric Marble, and the OPRD staff at the Thompson’s Mills.
![]() |
| Sodom Dam Deconstruction and Fish Salvage -Click photo to view album- |
out of Eugene was subcontracted by BCI Contracting to remove the dam. The process went smoothly as the concrete of the dam itself was quite brittle with little rebar. The site looks completely different without the dam (or the water!) The 24-inch HDPE bypass pipe will stay in place until the construction is finished in 2 months. We are maintaining approximately 10 cfs
of flow in the Sodom Channel downstream of the site during construction.













